Door, Door Frame or Sash Erection – Metal or Metal Covered – All Operations to Completion

Description

Code 5102 applies to employers engaged in the erection or installation of metal or metal covered doors or door frames, including fireproof doors, elevator bucks, revolving or shower doors, tub enclosures and non-overhead type garage doors.  The operations include placement and securing by bolting, riveting or welding.  The doors may be trimmed for proper clearance, and latching mechanisms are installed. The replacement of existing doors may require the replacement of damaged or deteriorated sashes.

This classification includes erection of railings or fencing above the first story level.

Assignment by Analogy

Solar panel installation

Operations to be Separately Rated

  1. Installation or erection:
    1. Storm windows or doors.  Refer to Code 5428 “Storm Door, Storm Sash, Screens or Weather-Stripping Installation – All Operations to Completion.”
    2. Garage, overhead or roll-up doors including automatic opening devices.   Refer to Code 3724 “Machinery or Equipment Erection or Installation – NOC – All Operations to Completion & Drivers.”
    3. Iron or steel balconies, fire escapes, fire proof shutters and staircases on the exterior of buildings and bridge roadway plates or grates.  Refer to Code 5040 “Iron or Steel Erection – Frame Structures – All Operations to Completion.”
    4. Railings or fencing on building exteriors from ground level and up to the first story.  Refer to Code 6400 “Fence Erection – Metal – All Operations to Completion.”
    5. Greenhouses.  Refer to Code 5402 “Greenhouse Erection – All Operations to Completion.”
    6. Architectural wood windows or doors.  Refer to Code 5429 “Cabinet Works Installation – All Operations to Completion.”
  2. Replacing broken window or glass.  Refer to Code 5462 “Glazier – Away From Shop – All Operations to Completion & Drivers.”

  3. Electrical work associated with solar panel installation.  Refer to Code 5190 “Electrical Wiring – Within Buildings – All Operations to Completion & Drivers.”

  4. Plumbing work associated with solar panel installation.  Refer to Code 5183 “Plumbing – NOC – All Operations to Completion & Drivers.”

Industry Group

Contracting